Week 16_450WEEK 16:

On Tuesday of this week the tripple glazed aluclad windows and sliding screens arrived on site. They were installed over the past couple of days. This means that finishes internally can be completed throughout the house. The plaster work (both slabbing and skimming) has been completed throughout meaning the electrical and mechanical second fix is well under way. This will be completed in the coming days. The fitting of all internal doors, skirting & architraves can also now commence.

Externally, the remaining walls of the original house and extension have been fully wrapped with insulation allowing the acrylic render to be completed throughout.

Click here to read more about this project.